What is construction adjudication?
Adjudication is a statutory dispute resolution procedure for construction contracts in the UK. It was introduced by Part II of the Housing Grants, Construction and Regeneration Act 1996 (the "Construction Act"), which came into force on 1 May 1998, and was amended in England and Wales by Part 8 of the Local Democracy, Economic Development and Construction Act 2009 for contracts entered into on or after 1 October 2011.
A party to a construction contract within the Act has the right to refer a dispute to adjudication at any time. If the contract does not contain compliant adjudication provisions, the relevant parts of the Scheme for Construction Contracts are implied into it.
How the process works
- Notice of Adjudication. The referring party gives written notice of its intention to refer a dispute, describing the dispute and the redress sought.
- Appointment. An adjudicator is named in the contract, agreed between the parties, or nominated by an adjudicator nominating body.
- Referral. The referral notice, with supporting documents, must be served within seven days of the notice of adjudication.
- Response and submissions. The responding party answers, and the adjudicator may request further submissions, documents or a meeting.
- Decision. The adjudicator must reach a decision within 28 days of the referral. This can be extended by up to 14 days with the referring party's consent, or longer if both parties agree.
The decision is binding until the dispute is finally determined by legal proceedings, arbitration or agreement. If it is not paid, the successful party can usually enforce it through the Technology and Construction Court by way of summary judgment.
Payment disputes, smash and grab and true value
Most adjudications concern money. The Construction Act requires payment notices and, where the payer intends to pay less than the sum due, a valid pay less notice served in time. Where a payer fails to serve the required notices, the "notified sum" may become payable regardless of the true value of the work — the basis of so-called smash and grab adjudications.
A payer who has missed its notices may later bring a true value adjudication to establish what was actually due. Following the Court of Appeal's decision in Grove Developments Ltd v S&T (UK) Ltd [2018] EWCA Civ 2448, the payer must generally pay the notified sum before it can pursue a true value adjudication. Timing, notices and contract terms all matter, and each case turns on its facts.
Disputes commonly referred
- Interim and final account valuations
- Payment notices and pay less notices
- Variations and additional work
- Extensions of time and liquidated damages
- Loss and expense
- Defects and the cost of remedial work
- Termination and repudiatory breach
Who adjudication does not cover
Contracts with a residential occupier for work on the dwelling they live in, or intend to live in, are excluded from the statutory scheme. Homeowners and their builders can still agree to adjudication by including an adjudication clause in their contract.
How Steve can help
Steve holds a Diploma in Adjudication and is a member of the Adjudication Society. He can be appointed as adjudicator by agreement of the parties or through a nominating body, or instructed to advise and represent a referring or responding party — preparing the notice, referral or response, assembling the evidence and dealing with the adjudicator's directions.
Independent appointment or party representation — never both. Steve may be appointed as the independent decision-maker in a dispute, or instructed to advise and represent one party. These are distinct roles. On any one matter he acts in one capacity only, and he will decline an instruction where there is a conflict of interest.
